The drainage works we carried out on behalf of Waco UK Ltd involved a live sewer connections at the Essex college. Our experienced sewer gang connected a temporary accommodation block to the main sewer, and the surface water drainage system to the surface water outlet.
We excavated fifteen meters of trench up to a depth of 2.5 meters to enable the foul drain run to be picked up from the building and be connected to the Essex public sewer. 150mm diameter super sleeve pipe was installed along with 2 new inspection chamber consisting of 1.2 meter diameter chambers.
As with all drainage and sewer works meticulous planning and experience is vital due to the potential dangers involved with these works. The Essex groundworks project was completed on time, safely and to a high standard.